GAZİANTEP-ŞANLIURFA MOTORWAY
GAZİANTEP-BİRECİK SECTION

TUBİN – TEKFEN - ÖZDEMİR JOINT VENTURE

( Km : 0+000.00 – 53+400.00 )

Client : General Directorate of Turkish Highways ( TCK )
Commencement Date : 06.07.2000
Contract Completion Date : 12.05.2004

The project which is in the scope of TEM ( Trans-European Motorway ) scheme to join Europe to Middle East Countries and also GAP region (Southeastern Anatolia Project) to the harbors was tendered in 1998 and the construction works commenced in 2000.

  • Length of the Motorway : 2 x 3 ; 53 400 m
  • Connection Way : 3 600 m
  • Excavation : 11 800 000 m3
  • Fill : 12 150 000 m3

  • Hot Mix : 1 125 550 tonnes
  • Cold Mix : 3 100 000 tonnes
  • Viaduct : nos. 3 ; 2111 m
  • Fly-Overs : nos. 3
  • Underpass and Over-bridge : nos. 34
  • Box Culverts : nos. 92


ANKARA - POZANTI MOTORWAY
ÇİFTEHAN - POZANTI SECTION

TEKFEN-TUBİN—ÖZDEMİR JOINT VENTURE

( Km : 350+500.00 – 366+596.00 )

Client : General Directorate of Turkish Highways ( TCK )
Commencement Date : 09.06.2000
Contract Completion Date : 24.09.2004

The project which is the part of TEM ( Trans European Motorway ) scheme, connecting western Anatolia to the southern Anatolia starting from Ankara was tendered in 1998. Construction works commenced in 2000.

  • Length of the Motorway : 2 x 3 ; 16 500 m
  • Connection Roads : 2 600 m
  • Excavation Volume : 6 700 000 m3

  • Embankment Volume : 5 650 000 m3

  • Hot Mix : 370 000 tonnes
  • Cold Mix : 750 000 tonnes
  • Tunnel : nos. 2 ; 1 679 m
  • Viaduct : nos. 14 ; 8 846 m
  • Fly-Overs : nos. 4
  • Underpass and Over-bridge : nos. 34
  • Box Culverts : nos. 24


 


ANKARA-POLATLI-SİVRİHİSAR (1st Section) ROAD CONSTRUCTION

( Km : 16+300.00 – 25+837.00 )

Client : General Directorate of Turkish Highways ( TCK )
Commencement Date : 20.07.1998
Contract Completion Date : 26.09.2003

The road, which is within the boundaries of TCK 4th Regional Directorate connects Ankara to the Aegean Region. Since existing 2 lane highway has became insufficient for the traffic flow, project was tendered in 1998 and the construction works for upgrading to 2 x 4 lanes divided state highway have been started in the same year.

  • Length of the Highway : 2 x 4 ; 9 500 m
  • Excavation : 350 000 m3

  • Embankment : 500 000 m3
  • P. Mix. Sub-base : 125 000 tonnes
  • P. Mix. Base : 150 000 tonnes
  • P. Mix. Shoulder : 20 000 tonnes
  • Bituminous Base : 90 000 tonnes
  • Binder : 70 000 tonnes
  • Wearing Course : 43 000 tonnes
  • Box Culvert : nos. 14
  • Fly - Overs : nos. 2 ; 89.40 m ( 44.70 x 2 )

ERZİNCAN-PÜLÜMÜR ) JUNCTION – 12th REGION BOUNDARY

STATE HIGHWAY CONSTRUCTION

( Km : 39+450.00 – 88+922.00 )

Client : General Directorate of Turkish Highways ( TCK )
Commencement Date : 15.05.1998
Contract Completion Date : 14.10.2004

The Erzurum-Erzincan State Highway Construction within the boundaries of TCK’s 16th Regional Directorate, being one of the main arterial highways of Eastern Turkey had recently been proven to be insufficient under prevailing geometric conditions and generated increasing traffic flows.

Consequently, with the tender in 1997 the construction works for improving the geometry of the road and upgrading the standards of the road surfacing as bituminous hot mix have been progressing.

  • Length of the Highway : 1 x 2 ; 49 500 m

  • Earthwork : 1 850 000 m3
  • Sub-base : 180 000 m3
  • P. Mix. Base : 267 000 tonnes
  • Bituminous Base : 78 000 tonnes
  • Binder : 87 000 tonnes
  • Wearing Course : 75 000 tonnes
  • Bridge Construction : nos. 3 ; 440 m
  • Engineering Structures : 248 000 m3